An engineer contractor has commissioned a research survey with a cost of $10,000 so that he will know the feasibility of putting up a bid.
An engineer contractor has commissioned a research survey with a cost of $10,000 so that he will know the feasibility of putting up a bid. He has paid $6,000 so far. What amount of survey costs is relevant to his bid?
a.$6,000 already paid
b.$4,000 payable
c. None
d.$10,000 total survey cost