An external vendor is running one month late in delivering a product component needed for Activity H. Activity H has several months of float. What
An external vendor is running one month late in delivering a product component needed for Activity H. Activity H has several months of float. What is the best action to take? Double the resources on Activity H to keep the activity on track,Employ resources smoothing by using the float to delay the start of Activity H by one month Correct,Perform two later activities simultaneously to make up time,Replace the vendor by using integrated change control