An individual assigned to a begin a project task April 2nd is unable to start until April 8th. When the project manager reschedules the task,
An individual assigned to a begin a project task April 2nd is unable to start until April 8th. When the project manager reschedules the task, what will she do before rescheduling the incomplete work? Select an answer: change the Actual Finish date to April 8th change the Actual Start to April 8th change the Status Date to April 8th change the Status Date to April 2nd