An indoor garden project was supposed to be completed in 45 days with cost of $1.8M. A month has passed by and it is 20%

An indoor garden project was supposed to be completed in 45 days with cost of $1.8M.

A month has passed by and it is 20% under the planned budget, but the contractor has accomplished 90% of the currently planned work.

  1. What is the expected delay of completion?
  2. What is the forecast of project cost?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Small Business Management Launching & Growing Entrepreneurial Ventures

Authors: Justin Longenecker, William Petty, Leslie Palich, Frank Hoy

17th edition

9781285972565, 1133947751, 1285972562, 978-1133947752

More Books

Students also viewed these General Management questions

Question

At the generating station power is..........?

Answered: 1 week ago

Question

The maximum number of electrons in a shell can be?

Answered: 1 week ago

Question

True or false The entire human population shows variations?

Answered: 1 week ago

Question

National park in India?

Answered: 1 week ago

Question

How did the guard ant recognise this ant ?

Answered: 1 week ago