An indoor garden project was supposed to be completed in 45 days with cost of $1.8M. A month has passed by and it is 20%
An indoor garden project was supposed to be completed in 45 days with cost of $1.8M.
A month has passed by and it is 20% under the planned budget, but the contractor has accomplished 90% of the currently planned work.
- What is the expected delay of completion?
- What is the forecast of project cost?