An integrated electronic-chip manufacturer has a demand for a specific component of 800 parts per 8-hour day. The manufacturer wants to design a lean system
An integrated electronic-chip manufacturer has a demand for a specific component of 800 parts per 8-hour day. The manufacturer wants to design a lean system using containers. The containers the manufacturer used for this component held 20 parts. It takes about 4 hours to round-trip a container from one work center to the next and back again. The manufacturer also wants to hold 10% of safety stock of this part in its system.
How many containers should the lean system be using?
a. 5
b. 10
c. 20
d. 22
e. 30
Step by Step Solution
3.40 Rating (166 Votes )
There are 3 Steps involved in it
Step: 1
Data Given Demand D 100 partshour Le...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get StartedRecommended Textbook for
Operations Management A Supply Chain Process Approach
Authors: Joel D. Wisner
1st edition
978-1506354187, 1506354181, 1483383067, 978-1483383064
Students also viewed these Accounting questions
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
View Answer in SolutionInn App