Question

1 Approved Answer

An integrated electronic-chip manufacturer has a demand for a specific component of 800 parts per 8-hour day. The manufacturer wants to design a lean system

An integrated electronic-chip manufacturer has a demand for a specific component of 800 parts per 8-hour day. The manufacturer wants to design a lean system using containers. The containers the manufacturer used for this component held 20 parts. It takes about 4 hours to round-trip a container from one work center to the next and back again. The manufacturer also wants to hold 10% of safety stock of this part in its system.

How many containers should the lean system be using?

a. 5

b. 10

c. 20

d. 22

e. 30

Step by Step Solution

3.40 Rating (166 Votes )

There are 3 Steps involved in it

Step: 1

Data Given Demand D 100 partshour Le... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management A Supply Chain Process Approach

Authors: Joel D. Wisner

1st edition

978-1506354187, 1506354181, 1483383067, 978-1483383064

More Books

Students also viewed these Accounting questions

Question

=+ (b) What are the fan speed and power?

Answered: 1 week ago

Question

What is the effect of word war second?

Answered: 1 week ago

Question

What is a servicescape ?

Answered: 1 week ago

Question

What is the objective of material flow analysis?

Answered: 1 week ago