An organization planned to use $97 of direct materials per unit of output, but it actually used $95 per unit. During this period, the
An organization planned to use $97 of direct materials per unit of output, but it actually used $95 per unit. During this period, the company planned to make 2,850 units, but produced only 2,500 units. The flexible budget amount for direct materials cost is