Question

1 Approved Answer

An organization that tries to get the best possible estimates before responding to RFP s . Assuming that the ends of a range of estimates

An organization that tries to get the best possible estimates before responding to RFPs. Assuming that the ends of a range of estimates are +/3 sigma from the mean, which of the following range estimates involves the least risk?
A.30 days, plus or minus 5 days
B.22 to 30 days
C. Optimistic =26 days, most likely =30 days, pessimistic =33 days
D. Mean of 28 days

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management Achieving Competitive Advantage

Authors: Jeffrey K. Pinto

4th edition

133798070, 978-0133798074

More Books

Students also viewed these General Management questions