An owner has a small building constructed by a contractor using a CPFF contract. The contractor estimated the material cost at $81000 and the came

An owner has a small building constructed by a contractor using a CPFF contract. The contractor estimated the material cost at $81000 and the came up with a fixed fee of $41000 which includes all the labour cost estimates, When the project finished the actual material cost in $124000 but the contractor has made an extra claim to the owner of $12000 for extra labour because the owner changed their mind 3 times on the installation method of some items in the project. An arbitrator was used and determines that the contractor is 43% at fault for the extra labour from the changes. What does the owner pay the contractor? Hint, make sure you are clear on how much money each party is responsible for in the claim.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Core Concepts Of Accounting Information Systems

Authors: Nancy A. Bagranoff, Mark G. Simkin, Carolyn Strand Norman

11th Edition

9780470507025, 0470507020

More Books

Students also viewed these Accounting questions

Question

Describe what a controller and evaluator do.

Answered: 1 week ago

Question

=+ 4. How can policymakers infl uence a nations saving rate?

Answered: 1 week ago