Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Analytics Exercise 4 - 4 ( Algo ) You work for a company that makes cell phones and have been made project manager for the

Analytics Exercise 4-4(Algo)
You work for a company that makes cell phones and have been made project manager for the design of a new cell phone. Your
supervisors have already scoped the project, so you have a list showing the work breakdown structure, and this includes major project
activities. You must plan the project schedule and calculate project duration. Your boss wants the schedule on his desk tomorrow
morning!
You have been given the information in Exhibit 4.13. It includes all the activities required in the project and the duration of each
activity. Also, dependencies between the activities have been identified. Remember that the preceding activity must be fully
completed before work on the following activity can be started.
Your project is divided into five major subprojects. Subproject "P" involves developing specifications for the new cell phone. Here,
decisions related to such things as battery life, size of the phone, and features need to be made. These details are based on how a
customer uses the cell phone. These user specifications are redefined in terms that have meaning to the subcontractors that will
actually make the new cell phone in subproject "S" supplier specifications. These involve engineering details for how the product will
perform.
The individual components that make up the product are the focus of subproject "D." Subproject "I" brings all the components
together, and a working prototype is built and tested.
Finally, in subproject "V," suppliers are selected and contracts are negotiated.
Exhibit 4.13: Work Breakdown Structure and Activities for the Cell Phone Design Project
a. Determine the minimum number of weeks for completing the project.
Answer is complete but not entirely correct.
Minimum number of
weeks
b. Your boss would like you to study the impact of making two changes to how the project is organized. The first change involves
using dedicated teams that would work strictly in parallel on the activities in each subproject. For example, in subproject P(product
specifications) the team would work on P1, P2, P3, and P4 all in parallel. In other words, there would be no precedence relationships
within a subproject-all tasks within a subproject would be worked on at the same time and each would take the same amount of time
as originally specified. With this new design, all the subprojects would be done sequentially with P done first, then S, D, I, and finally V.
What would be the expected impact on how long it would take to complete the project if this change were made?
Answer is complete but not entirely correct.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Organization Theory And Public Management

Authors: Jonathan R. Tompkins

1st Edition

053417468X, 978-0534174682

More Books

Students also viewed these General Management questions

Question

Describe the new structures for the HRM function. page 676

Answered: 1 week ago