Another branch of GABA company has provided you with the following information regarding their routs and costs. Destinations Origins Pittsburgh Chicago San Jose Supply Chattanooga

Another branch of GABA company has provided you with the following information regarding their routs and costs.
Destinations
Origins Pittsburgh Chicago San Jose Supply
Chattanooga 3428373250
Memphis 4828583750
Nashville 5260423000
Demand 550025002000
There has been an increase in demand, and the company is planning to open a new production factory either
in Minneapolis or in Little Rock to meet extra demand of 4500 cases per week.
If the factory is built in Little Rock, the transportation costs to the three destinations are:
Factory Pittsburgh Chicago San Jose
Little Rock 446423
If the factory is built in Minneapolis, the transportation costs to the three destinations are:
Factory Pittsburgh Chicago San Jose
Minneapolis 464261
Where should the company build the new factory? Show your complete work.
Total Cost
Solve this problem and write the total cost here.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Natural Resource Management Reimagined

Authors: Robert G. Woodmansee

1st Edition

1108740138, 978-1108740135

More Books

Students also viewed these General Management questions