Question
ANSWER BOTH PLEASE :) The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item
ANSWER BOTH PLEASE :)
The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand.
Item | Lead Time | Amount on Hand | Direct Components | |||
End | 3 | 0 | L(2), C(1), K(3) | |||
L | 3 | 9 | B(2), J(3) | |||
C | 4 | 12 | G(2), B(2) | |||
K | 4 | 18 | H(4), B(2) | |||
B | 3 | 29 | ||||
J | 4 | 30 | ||||
G | 4 | 7 | ||||
H | 2 | 0 | ||||
Click here for the Excel Data File
a. If 43 units of the end item are to be assembled, how many additional units of B are needed? (Hint: You dont need to develop an MRP plan.)
b. An order for the end item is scheduled to be shipped at the start of week 16. What is the latest week that the order can be started and still be ready to ship on time? (Hint: You dont need to develop an MRP plan.)
Assume you are the manager of a shop that assembles power tools. You have just received an order for 52 chain saws, which are to be shipped at the start of week 8. Pertinent information on the saws follows:
Item | Lead Time (weeks) | On Hand | Components | |
Saw | 2 | 15 | A(2), B(1), C(4) | |
A | 1 | 10 | E(3), D(1) | |
B | 2 | 5 | D(2), F(3) | |
C | 2 | 65 | E(2), D(2) | |
D | 1 | 20 | ||
E | 1 | 10 | ||
F | 2 | 30 | ||
Develop the material requirements plan for component E using lot-for-lot ordering for all items. (Leave no cells blank - be certain to enter "0" wherever required.)
The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Click here for the Excel Data File a. If 43 units of the end item are to be assembled, how many additional units of B are needed? (Hint. You don't need to develop an MRP plan.) b. An order for the end item is scheduled to be shipped at the start of week 16 . What is the latest week that the order can be started and still be ready to ship on time? (Hint. You don't need to develop an MRP plan.) Assume you are the manager of a shop that assembles power tools. You have just received an order for 52 chain saws, which are to be shipped at the start of week 8 . Pertinent information on the saws follows: Develop the material requirements plan for component E using lot-for-lot ordering for all items. (Leave no cells blank - be certain to enter " 0 " wherever required.)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started