Question

1 Approved Answer

Answer is 4.5. Can someone explain the steps to get to the answer? 70) A project is represented by the activity durations (estimated at 90%

Answer is 4.5. Can someone explain the steps to get to the answer?

image text in transcribed

70) A project is represented by the activity durations (estimated at 90% likelihood of completion) and precedence requirements shown in the table. What is the length of the feeder buffer if this project is managed using critical chain methodology? ActivityPredecessor LengthActivity PredecessorLength 20 DB 200 10FD, E 16 13 70) A project is represented by the activity durations (estimated at 90% likelihood of completion) and precedence requirements shown in the table. What is the length of the feeder buffer if this project is managed using critical chain methodology? ActivityPredecessor LengthActivity PredecessorLength 20 DB 200 10FD, E 16 13

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Databases questions

Question

Define Management by exception

Answered: 1 week ago

Question

Explain the importance of staffing in business organisations

Answered: 1 week ago

Question

What are the types of forms of communication ?

Answered: 1 week ago

Question

Explain the process of MBO

Answered: 1 week ago

Question

How do Data Types perform data validation?

Answered: 1 week ago

Question

How does Referential Integrity work?

Answered: 1 week ago