Answered step by step
Verified Expert Solution
Link Copied!

Question

00
1 Approved Answer

Answer the following cases with the particular type-Float. Assume that A is the activity which has a successor 'S. State the validity along with respective

Answer the following cases with the particular type-Float. Assume that A is the activity which has a successor 'S.

State the validity along with respective reasons:

1.Amount of time by which the actual completion of A can exceed its earliest expected time of completion without any delay of the project.

2.Latest start time minus earliest start time of A.

3.Value by which A can be delayed beyond its earliest start point without affecting earliest start time of S.

4.Latest finish time of A minus earliest start time of S.

5. Resource leveling aims at smoothening of the resource usage rate without changing the project duration.

6.Two actvities have common predecessor and successor activities. So, they can have common initial and final nodes.

7.In respect of any activity whether real or dummy, the terminal node should bear a number higher than the initial node number.

8.The optimal duration of a project is the minimum time in which it can be completed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managerial Accounting

Authors: Ray Garrison, Eric Noreen, Peter Brewer

15th edition

1259404781, 007802563X, 978-1259404788, 9780078025631, 978-0077522940

Students also viewed these Accounting questions