Question
Answer the following cases with the particular type-Float. Assume that A is the activity which has a successor 'S. State the validity along with respective
Answer the following cases with the particular type-Float. Assume that A is the activity which has a successor 'S.
State the validity along with respective reasons:
1.Amount of time by which the actual completion of A can exceed its earliest expected time of completion without any delay of the project.
2.Latest start time minus earliest start time of A.
3.Value by which A can be delayed beyond its earliest start point without affecting earliest start time of S.
4.Latest finish time of A minus earliest start time of S.
5. Resource leveling aims at smoothening of the resource usage rate without changing the project duration.
6.Two actvities have common predecessor and successor activities. So, they can have common initial and final nodes.
7.In respect of any activity whether real or dummy, the terminal node should bear a number higher than the initial node number.
8.The optimal duration of a project is the minimum time in which it can be completed
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started