Answer the following question with respect to MS project 1)The task named 'Design wireframe' is estimated to take 8 days. The task type is Fixed
Answer the following question with respect to MS project
1)The task named 'Design wireframe' is estimated to take 8 days. The task type is Fixed Work. Carole is assigned to work 100% of her time for 64 hours. Change the units to 200%. What is the new duration??
2)What is the term used to describe the black bars below the Gantt bars in the diagram below?