answer the question Assume the following: The standard tabor rate per hour is $17.00 The standard labor-hours allowed per unit of finished goods is 3
answer the question
Assume the following: The standard tabor rate per hour is $17.00 The standard labor-hours allowed per unit of finished goods is 3 hours . The actual quantity of labor hours worked during the period was 44.000 hours, The labor rate variance is $19.000 F. The company produced 15,000 units of finished goods during the period The actual direct labor wage rate per hour is closest to: Multiple Choice $16.32 $16.57 $16.07 $15.82 Step by Step Solution
There are 3 Steps involved in it
Step: 1