Answer this question with respect to the PERT problem posted in Canvas ( Test 1 0 Output document above ) . What is the variance

Answer this question with respect to the PERT problem posted in Canvas (Test 10 Output document above). What is the variance of task C?
Management Science
PERT OUTPUT : The following estimates of activity times (in days) are available for a small project.
\table[[Activity,Optimistic,Most Likely,Pessimistic],[A,4,5,6],[B,8,9,10],[C,7,7.5,11],[D,7,9,10],[E,6,7,9],[F,5,6,7]]
Answering the following questions first will give you an early start for your test.
a) Compute the expected completion time and variance for each activity.
b) An analyst has determined that the project's critical path consists of B-D-F. Compute the expected project completion time and standard deviation of project completion time.
c) What is the probability that the project will complete before 27 days?
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Business Research Methods

Authors: Emma Bell, Bill Harley, Alan Bryman

5th Edition

0198809875, 9780198809876

More Books

Students also viewed these General Management questions