Anvils Works' requires, on average, 2,600 tons of aluminum each week, with a standard deviation of 900 tons. The lead time to receive its orders
Anvils Works' requires, on average, 2,600 tons of aluminum each week, with a standard deviation of 900 tons. The lead time to receive its orders is 10 weeks. The holding cost for one ton of aluminum for one week is $10. It operates with a 0.98 in-stock probability. a. On average, how many tons does it have on order? Note: Round your answer to nearest integer. b. On average, how many tons does it have on hand? Note: Round your answer to nearest integer. c. If its average inventory was 12,500 tons, what would be its average holding cost per week? Note: Round your answer to nearest integer. d. If its average inventory was 11,000 tons, what would be its average holding cost per ton of aluminum? Note: Round your answer to 2 decimal places. d. If its average inventory was 11,000 tons, what would be its average holding cost per ton of aluminum? Note: Round your answer to 2 decimal places. e. Suppose its on-hand inventory is 4,950 tons, on average. What in-stock probability does it offer to its customers? Hint: use the = NORM.S.DIST(z,1) Excel function. Note: Do not round intermediate calculations or your z value. Round your final answer to 4 decimal places
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started