Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Apollo Sports manufacturers fabric tents. The poles are purchased from a vendor, so the only part manufactured is the actual fabric tent. The company uses
Apollo Sports manufacturers fabric tents. The poles are purchased from a vendor, so the only part manufactured is the actual fabric tent. | ||||||
The company uses a standard cost system based on manufacturing 5,000 tents per month. Overhead is applied on a per-unit basis. In May, | ||||||
4,840 tents were produced. Management has a policy that all variances greater than 3% from standard should be investigated. Standard and | ||||||
actual costs are listed below: | ||||||
Standard | ||||||
Direct material | 18 yards at $3.20 per yard | |||||
Direct labor | 6.5 hours at $16.00 per hour | |||||
Overhead applied | $12.00 per tent | |||||
Actual | ||||||
Direct material | 86,550 yards at $3.25 per yard | |||||
Direct labor | 32,100 hours at $15.80 per hour | |||||
Actual overhead | $56,750 | |||||
Instructions: | ||||||
1. Compute the total, price, and quantity variances for both materials and labor. | ||||||
State if each variance is favorable or unfavorable. | ||||||
2. Compute the total, volume, and budget overhead variances. State if favorable | ||||||
or unfavorable. | ||||||
3. Prepare journal entries for the application of overhead, the actual overhead, | ||||||
and to record variances and close the overhead account. Note that on the actual | ||||||
overhead, you will not have individual expense account amount, so just list | ||||||
"various" for the expense accounts. | ||||||
4. Always label all of your work. | ||||||
SOLUTION: | ||||||
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started