(Appendix 12A ) Dresser Company uses time and material pricing. The time rate is $35 per hour. The material loading charge is 15% for ordering,
(Appendix 12A ) Dresser Company uses time and material pricing. The time rate is $35 per hour. The material loading charge is 15% for ordering, handling, and storing materials and 25% for desired profit on these materials. Given these data, what would be the total charge for a job that requires 2.5 hours of labour time and $70 in materials? (Round your final answer to the nearest whole dollar). Multiple Choice $182 $190 $172 $214