Appleton Pulp and Paper Mill Appleton Corporation is one of the largest forestproducts companies in the world, converting trees into three basic product groups: (1)

Appleton Pulp and Paper Mill

Appleton Corporation is one of the largest forestproducts companies in the world, converting trees into three basic product groups: (1) building materials, such as lumber and plywood; (2) white paper products, including printing and writing grades of white paper; (3) brown paper products, such as liner-board and corrugated containers. Given the highly competitive markets within the forest-products industry, survival dictates that Appleton maintains its position as a low-cost producer of quality products. That requires an ambitious capital program to improve the timber base and to build modern, cost-effective timber conversion facilities.

An integrated pulp and paper mill is a facility in which wood chips and chemicals are processed to produce paper products or dried pulp. First, wood chips are cooked and bleached in the pulp mill; the resulting pulp is piped directly into storage tanks, as shown in Exhibit 10.11. From the storage tanks the pulp is sent to either the paper mill or a dryer. Any excess pulp not allocated to the paper mill or dryer is stored in the storage tanks until the next day. In the paper mill, the pulp is converted to finished paper products. Alternatively, the pulp is sent to a dryer, and the dried pulp is then sold to paper mills that do not have the capability of producing their own pulp. The profit margin is higher for dried pulp, so it is important to fully utilize the dryer capacity. The total system is a large facility costing several hundred million dollars.

Exhibit 10.11

Pulp and Paper Process

The pulp mill has a capacity of 800 tons per day (TPD), the paper mill has a capacity of 600 TPD of pulp use, and the dryer can handle 200 TPD. However, all of the equipment in the mill is subject to downtime for maintenance and reliability breakdowns. The pulp mill is assumed to have an average of 10 percent downtime. The actual downtime varies between 0 and 20 percent each day. For example, one day the pulp mill might be down 2 percent of the time, the next day 20 percent, and so on. In the paper mill, downtime averages 5 percent of the total working hours and may vary between 0 and 10 percent each day. Dryer downtime averages 15 percent and may vary from 0 to 30 percent each day. (Such situations can be modeled as uniform probability distributions; see Supplements A, Probability and Statistics, and G, Simulation.) Because of downtime, any pulp that has been allocated to the paper mill or dryer but cannot be produced is discarded.

Storage tank capacity is limited to 800 TPD. If the storage tanks become full, pulp mill production stops for the day. On any day, once all pulp has been produced or the storage tanks become full, the pulp is sent to the paper mill or dryer for processing. Production at the pulp mill resumes the next day.

Case Questions for Discussion:

For all questions, develop and use a spreadsheet simulation model for your analysis. Use the approaches described in Supplements A and G to develop the probability distributions and implement the simulation model.

  1. At the beginning of day one, 75 tons are remaining in the storage tank. At the current capacities (base case), what is the average amount of pulp lost at the dryer and paper mill over a month (30-days)?
  2. What will happen to the estimated amount of pulp lost per month if (treat each question independently of the others)

A. the pulp mill capacity decreases to 700 from the base case?

B. pulp mill capacity increases to 900 from the base case?

C. pulp mill capacity increases to 1,000 or more from the base case?

D. the paper mill capacity increases to 700 from the base case?

E. storage tank capacity increases to 1,000 from the base case?

F. dryer capacity is increased to 300 from the base case? Explain what effect this has on paper mill production.

3.What is the impact of improving reliability to the point where downtime is zero at all facilities?

4.Using the results from question 2, summarize the impact of increasing capacities at the pulp mill, paper mill, dryer, and storage tank from the base case.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

ERP Digital License Management Audit And Compliance

Authors: Gangesh Thakur, Jay Kalaimani

1st Edition

1799104079, 978-1799104070

More Books

Students also viewed these Accounting questions

Question

Which version of IP is the most prevalent today?

Answered: 1 week ago