Are you able to calculate the below question without using excel? Compute the IRR staticfor Project E. The appropriate cost of capital is 7 percent.
Are you able to calculate the below question without using excel?
Compute the IRR staticfor Project E. The appropriate cost of capital is 7 percent.(Do not round intermediate calculations and round your finalanswer to 2 decimal places.)
Project ETime: 0 1 2 3 4 5
Cash flow-$2,000 $750 $780 $720 $500 $300
Should the project be accepted or rejected?
- accepted
- rejected