Question

1 Approved Answer

A.Resource leveling aims at smoothening of the resource usage rate without changing the project duration. B.Two actvities have common predecessor and successor activities. So, they

A.Resource leveling aims at smoothening of the resource usage rate without changing the project duration.

B.Two actvities have common predecessor and successor activities. So, they can have common initial and final nodes.

C.In respect of any activity whether real or dummy, the terminal node should bear a number higher than the initial node number.

D.The optimal duration of a project is the minimum time in which it can be completed.

E.Amount of time by which the actual completion of A can exceed its earliest expected time of completion without any delay of the project.

F.Latest start time minus earliest start time of A.

G.Value by which A can be delayed beyond its earliest start point without affecting earliest start time of S.

H.Latest finish time of A minus earliest start time of S.

Float type: Assume the activity A has successor S. Validate the items given.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Advanced Financial Accounting An IFRS Standards Approach

Authors: Pearl Tan, Chu Yeong Lim, Ee Wen Kuah

4th Edition

9789814821278, 9814821276

More Books

Students also viewed these Accounting questions

Question

Find the frequency domain voltage V0 as shown. Ao06-701

Answered: 1 week ago

Question

What reward will you give yourself when you achieve this?

Answered: 1 week ago