As a construction manager, you are asked to develop detailed time and cost plans for the construction of a new football stadium, with a gross
As a construction manager, you are asked to develop detailed time and cost plans for the construction of a new football stadium, with a gross floor area of m in Lincoln City.
Task A: Using the following information and costs from a similar project that you built in in the South East of England, prepare a detailed cost plan for the proposed stadium in Lincoln in Marks
Regional Stadium Cost Model
costm
gross floor area
Substructure
Frame
Upper Floors
Roof
Stairs
External walls, windows and doors
Internal walls and partitions
Internal doors, wall, floor & ceiling finishes
Furniture and fittings
Building Services
Total construction cost
MSc Construction Science and Management BTEM
The external works are budgeted to cost m
To this sum needs to be added for preliminaries, overheads and a contingency.
From your experience you estimate that costs in the East Midlands of England are cheaper than those in the South East. Adjust your budget accordingly.
Assuming an average inflation rate of per year from to adjust your budget accordingly.
Task B: Develop a programme for the project based upon the following information and criteria. Marks ID Activity Information and Criteria
Mobilisation
weeks
Substructure
Allow weeks
Frame
The steel frame is not available until week and will take weeks to complete
Upper Floors
The upper floors are precast concrete which will not be available until week Allow weeks for installation
Roof
Roofing work can commence weeks after the upper floors. Allow weeks for completion
Stairs
Precast concrete stairs to be installed at the same time as the upper floors
External walls, windows and doors
External cladding to proceed weeks after the roof commence. Allow weeks for completion
Internal walls and partitions
To commence as soon as the structure is watertight after activity Allow weeks
Internal doors, wall, floor & ceiling finishes
To commence weeks after the Internal walls and partitions. Allow weeks for completion
Furniture and fittings
Fitting out to commence weeks after activity has commenced. Allow weeks
Building Services
Building services can commence weeks before the building is watertight. Installation to be completed weeks after activity is completed
Builders work in connection
BWIC to be completed as required and as Building Services are installed
Commissioning, final clean and handover
Allow weeks for final snagging after the completion of all other works
External works
External works to proceed, as weather allows, for completion at the same time as activity
MSc Construction Science and Management BTEM
Task C:
I.
Use the programme and the cost plan to produce cash flow forecast to give the cost of the project each month. Marks
i
Now sum the monthly costs to give the total value of the project each month Marks
ii
Now use this data to plot an S curve Marks
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started