Question

1 Approved Answer

As a starting point, please use the WBS in list format below.Note that 1.0 to 10.0 are some of the major deliverables of Rose Industries'

As a starting point, please use the WBS in list format below.Note that 1.0 to 10.0 are some of the major deliverables of Rose Industries' IT PMO which will be used at the stating point to develop our project schedule.

IT PMO

1.0 Project Management and Control

2.0 Hiring project team

3.0 Job redesign

4.0 Project Management training

5.0 People change management

6.0 PMO organization

7.0 Procedure development

8.0 Process redesign

9.0 Management reporting

10.0 Rollout plan for implementation

Your schedule needs to have a minimum of 50 lines. 10 lines have been provided above. The 40 additional lines required can be created by further breaking down the major deliverables above to summary tasks and sub-tasks and adding milestones.

Please make me a rough WBS for the above 10 tasks add sub tasks for each of them take the below WBS as reference while adding or framing the deliverables , and I should be able to differentiate which is a Major deliverable and which is a sub task.

This is my friend's WBS can you please make another one by changing the words, So that Plagiarism won't be caught.

  1. Project Management and Control
  2. Hiring project team
    1. Requirement gathering
    2. Prepare the human resource plan
    3. Obtain senior management approval
    4. Call for application
    5. Interviews
    6. Selection
    7. Team onboarding
    8. Orientation
  3. Job redesign
    1. Develop the Job Description
    2. Develop Designations
    3. Obtain senior management approval
  4. Project Management training
    1. Requirement gathering
    2. Develop a training calendar
    3. Assign training
    4. Test the learnings
    5. Reschedule more trainings
    6. Test the learnings
  5. People change management
    1. Develop a plan
    2. Obtain approval
    3. Resource allocation
    4. Execute the plan
    5. Monitor the progress
  6. PMO organization
    1. Develop Project Charter
    2. Approval for Project Charter
  7. Procedure development
  8. Process redesign
    1. Develop a plan
    2. Obtain approval
    3. Resource allocation
    4. Execute the plan
    5. Monitor the progress
  9. Management reporting
    1. Status Reporting Processes
    2. Develop Forms and Reports
    3. Monitor Progress
  10. Rollout plan for implementation
    1. Development
      1. Wire frame designs
      2. UI Designs
      3. Prototype designs
      4. App Development
      5. Web Development
    2. Testing
      1. User Acceptance Testing
      2. IT Vulnerability Testing
      3. Quality Assurance
    3. Parallel Trail Run
    4. Cut over and Go Live

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Law For Recreation And Sport Managers

Authors: Doyice J Cotten, John Wolohan

8th Edition

179244429X, 978-1792444296

More Books

Students also viewed these Law questions