As of this Monday, your projects BAC is 1800 person-hours, PV is 1080 person-hours, AC is 1320 person-hours, and EV is 1200 person-hours. Use a
As of this Monday, your projects BAC is 1800 person-hours, PV is 1080 person-hours, AC is 1320 person-hours, and EV is 1200 person-hours. Use a spreadsheet to perform the following EVA.
-
Find the values for the following EVA metrics: Cost Variance, Cost Performance Index, Schedule Variance, Schedule Performance Index, Estimate at Completion, Estimate to Completion, To-Complete Performance Index.
-
What is your likely course of action to get the project back on track in terms of cost and schedule?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started