Question

1 Approved Answer

As of this Monday, your projects BAC is 1800 person-hours, PV is 1080 person-hours, AC is 1320 person-hours, and EV is 1200 person-hours. Use a

As of this Monday, your projects BAC is 1800 person-hours, PV is 1080 person-hours, AC is 1320 person-hours, and EV is 1200 person-hours. Use a spreadsheet to perform the following EVA.

  1. Find the values for the following EVA metrics: Cost Variance, Cost Performance Index, Schedule Variance, Schedule Performance Index, Estimate at Completion, Estimate to Completion, To-Complete Performance Index.

  2. What is your likely course of action to get the project back on track in terms of cost and schedule?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The Complete Guide To Operational Auditing 1995 Supplement

Authors: Harry R. Reider

1st Edition

0471102547, 978-0471102540

More Books

Students also viewed these Accounting questions

Question

a. When did your ancestors come to the United States?

Answered: 1 week ago

Question

d. What language(s) did they speak?

Answered: 1 week ago

Question

e. What difficulties did they encounter?

Answered: 1 week ago