Answered step by step
Verified Expert Solution
Question
1 Approved Answer
As part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly operation to achieve an output
As part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly operation to achieve an output of 240 units per eight-hour day. Task times and precedence relationships are as follows: Click here for the Excel Data File Do each of the following: a. Determine the minimum cycle time, the maximum cycle time, and the calculated cycle time. (Round your answers to 1 decimal place.) b. Determine the minimum number of stations needed. (Round your answer to the next whole number.) c. Assign tasks to workstations on the basis of greatest number of following tasks. Use longest processing time as a tiebreaker. If ties still exist, assume indifference in choice. d. Compute the percentage of idle time for the assignment in part d. Use the actual bottleneck cycle time in your calculation. (Round your answer to 2 decimal places.)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started