As part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly line to achieve an output
As part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly line to achieve an output rate of units per eighthour day. Task times and precedence relationships are as follows:
Task Duration minutes Precedes Task
a b
b d
c d
d g
e f
f g
g
Do each of the following:
a This part of the question is not part of your Connect assignment.
b Determine the required cycle time.
Cycle time Numeric ResponseEdit Unavailable. incorrect. minutes per unit
c Determine the minimum number of workstations needed. Round the final answer to next whole number.
Number of workstations Numeric ResponseEdit Unavailable. incorrect.
d Assign the tasks to workstations using the heuristic rule Assign the task with the most followers. Use the heuristic rule Assign the task with the longest time as a tiebreaker. If a tie still exists, choose randomly. Do not leave any empty spaces; input a wherever it is required. Round the final answers to decimal place.
Workstation Task Idle time
e Calculate the percentage idle time for the assignments in part dRound the final answer to decimal places.
Percentage Idle time
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started