As the hurdle rate (i.e., the opportunity cost of capital) is increased, the NPV of a specific project will: A. stay the same B. increase
As the hurdle rate (i.e., the opportunity cost of capital) is increased, the NPV of a specific project will:
A. stay the same |
B. | increase |
C. | decrease |
D. decrease to zero, then remain constant |
E. | increase to zero, then remain constant |