As the production scheduler, you are to schedule an order of 100 items of A, which are to be shipped in week 10. Assume lot-for-lot
As the production scheduler, you are to schedule an order of 100 items of A, which are to be shipped in week 10. Assume lot-for-lot ordering. Below is the information about Item A and its components.
Item Lead Time On-Hand Components
A 2 10 B(3), E(2)
B 3 50 C(1), D(2)
C 1 20
D 2 40
E 2 15
Develop a net requirement plan for all items (use the attached template)