As the project manager of a website development project, you have just completed an analysis of project risks and have prioritized them using a probability
As the project manager of a website development project, you have just completed an analysis of project risks and have prioritized them using a probability and impact matrix. The approach you used to prioritize the risks is:
Question options:
a
Qualitative analysis
b
Quantitative analysis
c
Earned value analysis
d
Sensitivity analysis