Aspen Technologies has the following budget data: Estimated direct labor hours 11,100 Estimated direct labor dollars $57,200 Estimated factory overhead costs $166,100 If factory overhead
Aspen Technologies has the following budget data:
Estimated direct labor hours | 11,100 |
Estimated direct labor dollars | $57,200 |
Estimated factory overhead costs | $166,100 |
If factory overhead is to be applied based on direct labor hours, the predetermined overhead rate is
a.$22.45
b.$17.96
c.$11.97
d.$14.96