Assist with HW show all work 10. The estimated times and immediate predecessors for the activities in a project at John Black's company are given

Assist with HW show all work

10. The estimated times and immediate predecessors for the activities in a project at John Black's company are given in the following table. Assume that the activity times are independent. All times are in weeks.

Activity Predecessors Optimistic Time (a) Most Likely Time (m) Pessimistic Time (b)
A -- 2 4 6
B -- 1 2 9
C A 2 4 6
D B 5 8 17
E C 2 5 8

a, What is the critical path? You may use any method to determine this.

b. What is the expected completion time of the project? What is the expected total work time for this project?

c. What is the probability of completing the project in 15 weeks or longer?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Strategic Managerial Approach

Authors: Jack R. Meredith, Scott M. Shafer, Samuel J. Mantel Jr.

11th Edition

1119803837, 978-1119803836

More Books

Students also viewed these General Management questions

Question

=+b) Are the conditions for two-way ANOVA met?

Answered: 1 week ago

Question

What do you think is likely to be Liams problem? Discuss.

Answered: 1 week ago

Question

What laws were passed because of domestic violence?

Answered: 1 week ago