Assume a company had no jobs in progress at the beginning of July and no beginning inventories. It started and completed only two jobs during
Assume a company had no jobs in progress at the beginning of July and no beginning inventories. It started and completed only two jobs during JulyJob Y and Job Z. The company uses a plantwide predetermined overhead rate based on direct labor-hours. The following additional information from the month of July is available for the company as a whole and for Jobs Y and Z:
Estimated total fixed manufacturing overhead | $ | 13,000 | |
Estimated variable manufacturing overhead per direct labor-hour | $ | 1.00 | |
Estimated total direct labor hours to be worked | 2,000 | ||
Total actual manufacturing overhead costs incurred | $ | 12,800 | |
Job Y | Job Z | |||||
Direct materials | $ | 13,000 | $ | 8,000 | ||
Direct labor cost | $ | 21,000 | $ | 7,500 | ||
Actual direct labor hours worked | 1,400 | ? | ||||
Assuming Job Zs total job cost is $19,250, how many direct labor hours were actually worked on Job Z?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started