Assume Larry's Manufacturing was contracted to build a 5 story building for $2,250,000. The project began in 2016 and was completed in 2017. Data relating

Assume Larry's Manufacturing was contracted to build a 5 story building for $2,250,000. The project began in 2016 and was completed in 2017. Data relating to the contract are summarized below:

2016

2017

Costs incurred during the year

$320,000

$1,720,000

Estimated costs to complete as of 12/31

1,280,000

0

Billings during the year

405,000

1,670,000

Cash collections during the year

260,000

1,775,000

Required:

1.

Compute the template and journal entries for 2016 and 2017.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Auditing Today

Authors: Emile Woolf

6th Edition

0135894662, 978-0135894668

More Books

Students also viewed these Accounting questions

Question

5. Recognize your ability to repair and let go of painful conflict

Answered: 1 week ago