Assume that a project is at the end of the fourth month with a 75% rate of performance with $ 550,000.0 Actual Cost and $
Assume that a project is at the end of the fourth month with a 75% rate of performance with $ 550,000.0 Actual Cost and $ 400,000.0 Planned Cost Value. The BAC (budget at completion) was $950,000 for this one-year project. (6 points) (SO 02) 1. Calculate the estimate at completion (EAC) for this project? (2 points) 2. Estimate how long it will take to finish this project? (2 points) 3. How is the project doing concerning schedule and budget? (2 points) Attach your answer in handwritten format with the Vindows permitted types of files
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started