Question

1 Approved Answer

Assume that ABC Company has invested a budget of 36 million riyals for XY project and planned to complete in 12 months. In addition,

Assume that ABC Company has invested a budget of 36 million riyals for XY project and planned to complete in 12 months. In addition, assume that the company planned to spend the budget equally in each month. However, when the first two months has passed, the project manager has found out that the total of two million riyals spent. Based on the above scenario, answer the following: Suppose Rate of performance =0.25 a) What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? b) How much will it actually cost the company to complete this project, and how long will it really take to complete it based on the performance to date? c) What do you think of the project performance? over/under the budget? behind lahead the schedule? Justify your answer.

Step by Step Solution

3.38 Rating (160 Votes )

There are 3 Steps involved in it

Step: 1

Budgeted cost BAC 36 million riyals The company had planned to spen... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Corporate Finance A Focused Approach

Authors: Michael C. Ehrhardt, Eugene F. Brigham

4th Edition

1439078084, 978-1439078082

More Books

Students also viewed these Accounting questions