Assume the following 4 jobs, and the 3tuple is release time, execution time and deadline. Create an ad hoc schedule and comment: j1 = [0,
Assume the following 4 jobs, and the 3tuple is release time, execution time and deadline. Create an ad hoc schedule and comment:
j1 = [0, 1, 7]
j2 = [1, 3, 8]
j3 = [2, 2, 10]
j4 = [3, 1, 11]
2b. Calculate the following: response times for each job, overall average response time, median response time, mode response time, and overall set completion [execution] time. Can this set be done on one processor and why or why not?