Assume the following information: Probability of Failure Consequences of Failure Maturity = .3 Cost = .1 Complexity = .3 Schedule = .7 Dependency = .5
Assume the following information: Probability of Failure Consequences of Failure Maturity = .3 Cost = .1 Complexity = .3 Schedule = .7 Dependency = .5 Performance = .5 Calculate the overall risk factor for this project. Would you assess this level of risk as low, moderate, or high? Why?