Assume the project is 14 days old. TASK Percent Complete Expenditures/ Day Actual Expenditures to Date Duration A 100% $2,000 8 B 30% 9 70%
Assume the project is 14 days old. TASK Percent Complete Expenditures/ Day Actual Expenditures to Date Duration A 100% $2,000 8 B 30% 9 70% 7 $10,000 $9,000 $4,000 $5,000 $3,000 $0 D 80% $3,000 $2,000 $1,500 $1,500 $1,000 $1,200 6 E 0% 9 F 40% 7 G 0% $0 4 TASK TOTAL BUDGET %COMP ACWP (AC) BCWS (PV) BCWP (EV) CV SV CPI SPI B 100% 30% 70% D 80% E 0% 40% F G 0% Totals $0 BAC = TAC = Comments: EAC = ETAC = #DIV/0! #DIV/0