At a production level of 5 600 units a project has total costs of R89 000. The variable cost per unit is R11.20. What is
At a production level of 5 600 units a project has total costs of R89 000. The variable cost per unit is R11.20. What is the amount of the total fixed costs if the production level is increased to 6 100 units without increasing the total fixed assets?
Select one:
a.R28 626
b.R27 820
c.R24 126
d.R26 280
e.R27 090
Step by Step Solution
There are 3 Steps involved in it
Step: 1