Question

1 Approved Answer

At a WIP of 13,400, our average throughput is 892/hour. Our critical WIP is 185 and our bottleneck rate is 920/hour. What would you conclude

At a WIP of 13,400, our average throughput is 892/hour. Our critical WIP is 185 and our bottleneck rate is 920/hour. What would you conclude about our system?

Our throughput is lower than expected, based on the practical worst case.

Our throughput is higher than expected, based on the practical worst case.

We are outperforming the best case scenario.

The worst case is really all we can expect.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Research Methods For Managers

Authors: John Gill, Phil Johnson

4th Edition

1847870945, 9781847870940

More Books

Students also viewed these General Management questions