At a WIP of 13,400, our average throughput is 892/hour. Our critical WIP is 185 and our bottleneck rate is 920/hour. What would you conclude
At a WIP of 13,400, our average throughput is 892/hour. Our critical WIP is 185 and our bottleneck rate is 920/hour. What would you conclude about our system?
Our throughput is lower than expected, based on the practical worst case.
Our throughput is higher than expected, based on the practical worst case.
We are outperforming the best case scenario.