Question

1 Approved Answer

At a work centre, two types of jobs are to be done - 'A' and 'B'. 'A' needs a setup time of 20 minutes, and

At a work centre, two types of jobs are to be done - 'A' and 'B'. 'A' needs a setup time of 20 minutes, and a per piece time of 3 minutes. 'B' needs a setup time of 25 minutes, and a per piece time of 2 minutes. They have been alternating between ten units of A and ten units of B. 

Instead, if they alternate between 50 units of A and 50 units of B, what is the percentage increase in productivity? (Both A and B are priced equal, so for the total output, you can add the two; you can assume a continuous 24 hour operation)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

To calculate the percentage increase in productivity when alternating between 50 units of A and 50 u... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management Accounting Information for Decision-Making and Strategy Execution

Authors: Anthony A. Atkinson, Robert S. Kaplan, Ella Mae Matsumura, S. Mark Young

6th Edition

137024975, 978-0137024971

More Books

Students also viewed these General Management questions