At aproduction level of 4,500 units, a project has total costs of$108,000. The variable cost per unit is $11.20. Assume the firm canincrease production by
At aproduction level of 4,500 units, a project has total costs of$108,000. The variable cost per unit is $11.20. Assume the firm canincrease production by 1,000 units without increasing its fixedcosts. What will the total costs be if 4,800 units areproduced? A. $102,780 B. $104,640 C. $106,400 D. $108,000 E. $111,360