: At Briggs Company, the standard time required to assemble one transmitter is 2.30 hours. The standard wage is $9.60 per hour. During June, employees
: At Briggs Company, the standard time required to assemble one transmitter is 2.30 hours. The standard wage is $9.60 per hour. During June, employees at Briggs produced 860 transmitters and worked 1,935 labor hours at a total cost of $18,963. What is Briggss labor rate variance?