Question

1 Approved Answer

At Computer Labs Incorporated, where you work as a project manager, you have been asked to conduct user-training sessions for a new information system. You

At Computer Labs Incorporated, where you work as a project manager, you have been asked to conduct user-training sessions for a new information system. You must develop a specific schedule for the tasks. Use the information below to complete tasks

First, confirm arrangements for the training facility you plan to use (3 days).

After you have confirmed the training facility, two tasks can begin at the same time: you need to send an e-mail message to all department managers announcing the training sessions (1 day) and you can develop the training material (5 days).

As soon as the email has been sent and the training material is complete, you can work on two tasks at once: arrange to have copies of handout material printed (2 days) and develop a set of PowerPoint slides (5 days).

When the PowerPoint slides are ready and the handouts have been printed, conduct a practice training session with the instructor who will assist you (2 days).

When the practice session is over, conduct the user training sessions (4 days).

Tasks

Create a WBS

What is the critical path for this project? How do you know?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Readings In Database Systems

Authors: Michael Stonebraker

2nd Edition

0934613656, 9780934613651

More Books

Students also viewed these Databases questions

Question

How do Excel Pivot Tables handle data from non OLAP databases?

Answered: 1 week ago