At its plant in Florida, Just D Fruits trucks deliver oranges at the rate of 10,700 kg per hour, from 7 a.m. to 7 p.m.

At its plant in Florida, Just D Fruits trucks deliver oranges at the rate of 10,700 kg per hour, from 7 a.m. to 7 p.m.

The plant processes its oranges as soon as the first truck arrives at 7 am, at the rate of 6,450 kg per hour. Processing continues until all deliveries for the day have been processed.

Estimate how many hours are needed to complete the processing of a day's deliveries, ie. the number of hours between 7 am and the time at which the oranges delivered by the last truck will have been processed. For example, if you estimate that the transformation will end at 3:00 AM, you would enter 20.0.

Round the final answer to one decimal (if you got 20.25 hours, you would enter 20.3 and don't convert the 0.25 hours into minutes).

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Quantitative Methods For Business

Authors: David Anderson, Dennis Sweeney, Thomas Williams, Jeffrey Cam

12th Edition

840062338, 840062346, 9780840062338, 978-0840062345

More Books

Students also viewed these General Management questions