At Morgan's Transformer Rebuilding, five jobs are ready now for dispatching to a machine center. The processing times and due dates for the jobs
At Morgan's Transformer Rebuilding, five jobs are ready now for dispatching to a machine center. The processing times and due dates for the jobs are given below. Use earliest due date to sequence the jobs in the machine center. Job Work Time Due Date (days) (days) ABCDE 15 38 13 28 7 20 18 50 9 15 Calculate the average number of jobs in the machine center. 1.58 3.58 2.58 1.28