At the beginning of the project, it was expected to construct 100 ft2 of a wall by at a rate of $120 per ft2. As
At the beginning of the project, it was expected to construct 100 ft2 of a wall by at a rate of $120 per ft2. As per the initial plan it was planned to construct 75 ft2 of the wall by the end of two m