Ava needs to check how different requirements are prioritized in her current project as she has to manage two completely different requests of stakeholders. Where
Ava needs to check how different requirements are prioritized in her current project as she has to manage two completely different requests of stakeholders. Where could she find this information? (For Ref Only, Question #: PM-04214) Group of answer choices In stakeholder register In project management plan In activity list In project documents