Question
1 Approved Answer
b. Based on the following Net Present Values (NPVs) of four different project proposals, which project proposal(s) will you choose and why, if: (2 Marks)
b. Based on the following Net Present Values (NPVs) of four different project proposals, which project proposal(s) will you choose and why, if: (2 Marks) i. The proposals are mutually exclusive The proposals are independent Project Proposal Net Present Value (NPV) A - 2000 B 3500 4500 D (1500)